How JustAnswer Works:
  • Ask an Expert
    Experts are full of valuable knowledge and are ready to help with any question. Credentials confirmed by a Fortune 500 verification firm.
  • Get a Professional Answer
    Via email, text message, or notification as you wait on our site. Ask follow up questions if you need to.
  • 100% Satisfaction Guarantee
    Rate the answer you receive.
Ask Sandhya Your Own Question
Sandhya
Sandhya, Tutor
Category: Homework
Satisfied Customers: 3715
Experience:  I have several years of teaching experience.
14910578
Type Your Homework Question Here...
Sandhya is online now
A new question is answered every 9 seconds

Using the information provided in the table, the network diagram

This answer was rated:

Using the information provided in the table, the network diagram and the expected project completion time = 39 weeks:

Activity Opt. Time Most Likely Time Pessimistic Time

A 8 10 12
B 4 10 16
C 4 5 6
D 6 8 10
E 4 7 12
F 6 7 9
G 4 8 12
H 3 3 3

Network Diagram

B D F
A H
C E G

The critical path is A-B-D-G-H.


(a) Calculate the probability of completing the project in 36 weeks.

P(project ≤ 36) =

(b) Calculate the probability of completing the project in 40 weeks.

P(project ≤ 40) =

(Round your answers to 3 decimal places, the tolerance is +/-0.005.)
Hi,

Thanks for requesting me.

Data is not readable.

Please upload data in a file.

Thanks
Customer: replied 5 years ago.
Thanks for the file. I will try to send answer ASAP.

Thanks
Customer: replied 5 years ago.
Thanks!
I will send answers by evening time..

Thanks
Customer: replied 5 years ago.
Thank you!
Welcome!
THIS ANSWER IS LOCKED!

You need to spend $3 to view this post. Add Funds to your account and buy credits.
Sandhya and 2 other Homework Specialists are ready to help you