a. TV Assembler: As different sizes of TV sets are made but not according to the customer specification. Therefore batch process costing should be used.
b. Building Contractor: As each contract is different from other and buildings are made according to the specification of the customer therefore job order costing should be used.
c. Automobile repair shop: As each auto which is repaired requires different parts and each repair is of different duration therefore job order costing should be used.
d. Paper manufacturing: As the paper is made in bulk quantity and the product is of homogeneous nature and all goods are not made according to the specification of customer therefore process costing should be used.
e. Custom Jewelry manufacturer: As each and every order for jeweler to be made is different form other therefore job order costing should be used.