How JustAnswer Works:

  • Ask an Expert
    Experts are full of valuable knowledge and are ready to help with any question. Credentials confirmed by a Fortune 500 verification firm.
  • Get a Professional Answer
    Via email, text message, or notification as you wait on our site.
    Ask follow up questions if you need to.
  • 100% Satisfaction Guarantee
    Rate the answer you receive.

Ask Bizhelp Your Own Question

Bizhelp, CPA
Category: Multiple Problems
Satisfied Customers: 5852
Experience:  BA degree and Certified Public Accountant
Type Your Multiple Problems Question Here...
Bizhelp is online now
A new question is answered every 9 seconds

"For Bizhelp" Monday 6:30 PM EST

Customer Question

51. The two main challenges for virtual teams include ______________.

a. maintaining autonomy

b. automating monotony

c. building trust

d. the bullwhip effect

52. Virtual teams are often slowed down by difficulty with ______________.

a. superordinate goals

b. task reliance

c. punctuated equilibrium

d. communication

53. Project penalty clauses that initiate at mutually agreed-on points in the project’s

development and implementation are ______________.

a. liquidated damages

b. milestone adjustments

c. contingency clauses

d. penalty points

54. The firm set aside a little extra money just in case an unforeseen element of cost pushed the

project beyond what they had budgeted. This extra money is called a(n) ______________.

a. rainy day fund

b. contingency reserve

c. escalation clause

d. sinking fund

55. The mouse executive board meeting was drawing to a conclusion; the only way they would be able to detect the presence of the cat was to tie a bell around its tail. Under their risk management identification scheme, this would fall under ______________ risk.

a. commercial

b. execution

c. financial

d. technical

56. A method for conducting risk factor identification that consolidates the judgments of

isolated, anonymous respondents is _____________.

a. a brainstorming meeting

b. the Delphi method

c. past history

d. multiple assessments

57. A method for conducting risk factor identification that generates ideas but doesn’t focus on

decision-making is ______________.

a. a brainstorming meeting

b. the Delphi method

c. past history

d. multiple assessments

58. The consequences of failure categories of cost, schedule reliability and performance were

believed to be 0.2, 0.6, 0.5 and 0.7. What is the overall consequence of failure?

a. 0.2

b. 0.3

c. 0.4

d. 0.5

59. Input is received from an organization’s management to create a project budget in

______________ budgeting.

a. zero-based

b. top-down

c. bottom-up

d. activity-based

60. An advantage of top-down budgeting is ______________.

a. that top management estimates of project costs are often quite accurate, at least in

aggregate terms.

b. an elimination of the friction between top and lower levels in the competition for

budget money.

c. that projects are no longer a zero-sum game among lower level managers

d. top management budgets, by definition, cannot experience overruns

61. A budget that is created by starting with the work breakdown structure, determining costs for

each work package and then adding these costs together is ______________ budgeting.

a. zero-based

b. top-down

c. bottom-up

d. activity-based

62. When properly performed, bottom-up budgeting has the disadvantage of _____________.

a. a lack of detail needed in project plans

b. a lack of coordination among project managers and functional department heads

c. being a hindrance to top managers when prioritizing projects that are competing for

the same scarce resources

d. a reduction of top management’s control of the budget process to one of oversight

63. What learning rate is being demonstrated if the first unit takes 15 hours and the third unit

takes 14 hours to complete?

a. greater than or equal to 97 percent

b. less than 97 percent but greater than or equal to 95 percent

c. less than 95 percent but greater than or equal to 93 percent

d. less than 93 percent

64. It took 80 hours of analysis to complete the first phase, but the second phase was done in

74 hours. If this learning rate continues, then the 8th analysis should take a mere

____________ hours and ____________ minutes, give or take.

a. 63; 20

b. 68; 30

c. 57; 15

d. 52; 45

65. Which of these indirect costs is typically classified as an overhead cost?

a. advertising

b. shipping

c. sales commissions

d. taxes

66. These can be located by doing a backward pass through a network.

a. critical paths

b. merge activities

c. successors

d. burst activities

67. An activity with two or more immediate predecessors is a(n) _______________.

a. merge activity

b. burst activity

c. float activity

d. event

68. An activity has an optimistic time estimate of 7 days, a most likely estimate of 12 days and

a pessimistic estimate of 20 days. What is the expected standard deviation of the activity?

a. between 2 and 3

b. between 3 and 4

c. between 4 and 5

d. between 5 and 6

69. Activity Z has estimates a=5, b=10, m=7; activity X has estimates a=4, b=11, m=6; and

activity Y has estimates a=3, b=12, m=8. Which of the following statements is most


a. Activity X is longer than Activity Y

b. Activity X has a higher standard deviation than Activity Z

c. Activity Z is shorter than Activity Y

d. Activity Y has a smaller variance than Activity Z

70. There’s an old saying, “The job is not finished until the paperwork is done.” From an activity

network standpoint, this does not necessarily mean that the paperwork can’t begin until the

last non paperwork activity is completed. It might be possible to work on some paperwork as

early activities are completed. In order to depict this in an activity network, ______________.

a. hammock activities could be drawn

b. subroutines could be added

c. shortcuts can be added to the network

d. laddering could be used to redraw the network

71. One approach to reducing project length would be to ______________.

a. convert parallel paths to be serial

b. convert merge activities to burst activities

c. use hammock activities in place of multiple activities

d. eliminate tasks on the critical path

72. A project’s duration can be reduced by ______________.

a. shortening the duration of critical path tasks

b. adding tasks to the critical path

c. adding shorter routes around the critical path

d. completing the backward pass first

73. A basic Gantt chart _____________.

a. clearly displays early and late start and finish times for all activities

b. cannot be used to track the project’s progress

c. permits scheduling resources well before they are needed

d. shows dummy activities to preserve network logic

74. If an activity’s cost is plotted against its duration on axes with zeros at the origin, the slope

of the line is _____________.

a. positive because it costs more to finish an activity more quickly

b. negative because a shorter activity costs less than a longer one

c. negative because it costs more to finish an activity more quickly

d. positive because a longer activity costs more than a shorter one

75. An activity on arrow network _____________.

a. cannot have more arrows than nodes

b. cannot have more nodes than arrows

c. has one more node than arrows

d. has one more arrow than nodes

Submitted: 2 years ago.
Category: Multiple Problems
Expert:  Josie-Mod replied 2 years ago.
Hi, I'm Josie and I am a moderator for this topic. I sent your requested professional a message to follow up with you here, when he is back online.

If I can help further, please let me know. Thank you for your continued patience.
Expert:  Bizhelp replied 2 years ago.

Thanks for requesting me.

I am working on these and will answer by the deadline.
Expert:  Bizhelp replied 2 years ago.

Thanks for the questions.

Please click here to download the answers.

Hope this helps!
Bizhelp, CPA
Satisfied Customers: 5852
Experience: BA degree and Certified Public Accountant
Bizhelp and other Multiple Problems Specialists are ready to help you

JustAnswer in the News:

Ask-a-doc Web sites: If you've got a quick question, you can try to get an answer from sites that say they have various specialists on hand to give quick answers... seen a spike since October in legal questions from readers about layoffs, unemployment and severance.
Web sites like
...leave nothing to chance.
Traffic on JustAnswer rose 14 percent...and had nearly 400,000 page views in 30 days...inquiries related to stress, high blood pressure, drinking and heart pain jumped 33 percent.
Tory Johnson, GMA Workplace Contributor, discusses work-from-home jobs, such as JustAnswer in which verified Experts answer people’s questions.
I will tell you that...the things you have to go through to be an Expert are quite rigorous.

What Customers are Saying:

  • Wonderful service, prompt, efficient, and accurate. Couldn't have asked for more. I cannot thank you enough for your help. Mary C. Freshfield, Liverpool, UK
< Previous | Next >
  • Wonderful service, prompt, efficient, and accurate. Couldn't have asked for more. I cannot thank you enough for your help. Mary C. Freshfield, Liverpool, UK
  • This expert is wonderful. They truly know what they are talking about, and they actually care about you. They really helped put my nerves at ease. Thank you so much!!!! Alex Los Angeles, CA
  • Thank you for all your help. It is nice to know that this service is here for people like myself, who need answers fast and are not sure who to consult. GP Hesperia, CA
  • I couldn't be more satisfied! This is the site I will always come to when I need a second opinion. Justin Kernersville, NC
  • Just let me say that this encounter has been entirely professional and most helpful. I liked that I could ask additional questions and get answered in a very short turn around. Esther Woodstock, NY
  • Thank you so much for taking your time and knowledge to support my concerns. Not only did you answer my questions, you even took it a step further with replying with more pertinent information I needed to know. Robin Elkton, Maryland
  • He answered my question promptly and gave me accurate, detailed information. If all of your experts are half as good, you have a great thing going here. Diane Dallas, TX

Meet The Experts:

  • linda_us


    Master's Degree

    Satisfied Customers:

    A tutor for Business, Finance, Accounts and other related topics.
< Last | Next >
  • linda_us's Avatar


    Master's Degree

    Satisfied Customers:

    A tutor for Business, Finance, Accounts and other related topics.
  • F. Naz's Avatar

    F. Naz


    Satisfied Customers:

    have completed B.Com and CA Finalist
  • Mr. Gregory White's Avatar

    Mr. Gregory White

    Master's Degree

    Satisfied Customers:

    M.A., M.S. Education / Educational Administration
  • Manal Elkhoshkhany's Avatar

    Manal Elkhoshkhany

    Bachelor's Degree

    Satisfied Customers:

    Completed by BA degree in 1988 and graduated with a GPA of 4.0
  • Bizhelp's Avatar



    Satisfied Customers:

    BA degree and Certified Public Accountant
  • Alex's Avatar


    Bachelor's Degree

    Satisfied Customers:

    BS in Business Administration. Able to assist in various business related homework questions.
  • Dimitry K., Esq.'s Avatar

    Dimitry K., Esq.

    Doctoral Degree

    Satisfied Customers:

    JD/MBA, Business Attorney

Related Multiple Problems Questions