How JustAnswer Works:
  • Ask an Expert
    Experts are full of valuable knowledge and are ready to help with any question. Credentials confirmed by a Fortune 500 verification firm.
  • Get a Professional Answer
    Via email, text message, or notification as you wait on our site.
    Ask follow up questions if you need to.
  • 100% Satisfaction Guarantee
    Rate the answer you receive.
Ask Roger Your Own Question
Roger, Lawyer
Category: Intellectual Property Law
Satisfied Customers: 30898
Experience:  BV Rated by Martindale-Hubbell; SuperLawyer rating by Thompson-Reuters
Type Your Intellectual Property Law Question Here...
Roger is online now
A new question is answered every 9 seconds

Jughead Construction Company puts in a bid to build the new

Resolved Question:

Jughead Construction Company puts in a bid to build the new town library. Its bid is $1 million. The other bids range from $2 to $4 million, and the town's architect estimated to town officials that the library would cost about $3 million. The town accepts Jughead's bid offer. Jughead's best defense to any lawsuit for breach of contract under these circumstances would be:

Unilateral mistake

Fraud by the town for keeping the architect's estimate secret.

Bilateral mistake.

Submitted: 4 years ago.
Category: Intellectual Property Law
Expert:  Roger replied 4 years ago.
Hi - my name is XXXXX XXXXX I'm an Intellectual Property litigation attorney here to assist you.

It would be a unilateral mistake by Jughead if the bid calculations were incorrect.