How JustAnswer Works:

  • Ask an Expert
    Experts are full of valuable knowledge and are ready to help with any question. Credentials confirmed by a Fortune 500 verification firm.
  • Get a Professional Answer
    Via email, text message, or notification as you wait on our site.
    Ask follow up questions if you need to.
  • 100% Satisfaction Guarantee
    Rate the answer you receive.

Ask Sandhya Your Own Question

Sandhya, Tutor
Category: Homework
Satisfied Customers: 3711
Experience:  I have several years of teaching experience.
Type Your Homework Question Here...
Sandhya is online now
A new question is answered every 9 seconds

network diagram 39 weeks

This answer was rated:

Attachment: 2012-02-25_195359_39_weeks.docx



Using the information provided in the table, the network diagram and the expected project completion time = 39 weeks:


The critical path is A-B-D-G-H.

(a) Calculate the probability of completing the project in 36 weeks.

P(project ≤ 36) =

(b) Calculate the probability of completing the project in 40 weeks.

P(project ≤ 40) =

(Round your answers to 3 decimal places, the tolerance is +/-0.005.)


Thanks for requesting me.

I will send answer ASAP.


You need to spend $3 to view this post. Add Funds to your account and buy credits.
Sandhya and 3 other Homework Specialists are ready to help you

Related Homework Questions