How JustAnswer Works:

  • Ask an Expert
    Experts are full of valuable knowledge and are ready to help with any question. Credentials confirmed by a Fortune 500 verification firm.
  • Get a Professional Answer
    Via email, text message, or notification as you wait on our site.
    Ask follow up questions if you need to.
  • 100% Satisfaction Guarantee
    Rate the answer you receive.

Ask Sandhya Your Own Question

Sandhya
Sandhya, Tutor
Category: Homework
Satisfied Customers: 3713
Experience:  I have several years of teaching experience.
14910578
Type Your Homework Question Here...
Sandhya is online now
A new question is answered every 9 seconds

Use the following project information. Activity Activity

Resolved Question:

Use the following project information.

Activity Activity Time Immediate
(weeks) Predecessor(s)

A 3 none
B 4 A
C 2 B
D 5 B
E 4 C
F 3 D
G 2 E,F

Calculate the completion time for the project.

Completion time =_____________ weeks

Determine which activities are included on the critical path.


____ A, B, C, E, G


____ A, B, D, F, G
Submitted: 4 years ago.
Category: Homework
Expert:  Sandhya replied 4 years ago.
Hi,

Thanks for requesting me!

Tell me your deadline for this.

Thanks
Expert:  Sandhya replied 4 years ago.
THIS ANSWER IS LOCKED!

You need to spend $3 to view this post. Add Funds to your account and buy credits.
Sandhya and 3 other Homework Specialists are ready to help you

Related Homework Questions