Recent Feedback
1)Andre Candess manages an office supply store. One product in the store is computer paper. Andre
knows that 10,000 boxes will be sold this year at a constant rate throughout the year. There are 250
working days per year and the lead-time is 3 days. The cost of placing an order is $30, while the
holding cost is $15 per box per year. How many units should Andre order each time?
A)500
B)100
C)400
D)200
E)none of the above
2)R.C. Barker makes purchasing decisions for his company. One product that he buys costs $50 per
unit when the order quantity is less than 500. When the quantity ordered is 500 or more, the price
per unit drops to $48. The ordering cost is $30 per order and the annual demand is 7,500 units. The
holding cost is 10 percent of the purchase cost. If R.C. wishes to minimize his total annual
inventory costs, he must evaluate the total cost for two possible order quantities. What are these
two possible quantities? (Round answer to nearest unit.)
A)306 and 50
B)300 and 500
C)300 and 306
D)200 and 306
3)The demand during the lead time is normally distributed with a mean of 40 and a standard
deviation of 4. If they have calculated a reorder point of 46.60 units, what service level are they
assuming?
A)97.5 percent
B)85 percent
C)90 percent
D)95 percent
4)Which of the following does not have an impact on EOQ?
A)order cost
B)demand per unit time
C)safety stock
D)all of the above
5) The annual demand for a product has been projected at 2,000 units. This demand is assumed to be
constant throughout the year. The ordering cost is $20 per order, and the holding cost is 20 percent
of the purchase cost. Currently, the purchase cost is $40 per unit. There are 250 working days per
year. Whenever an order is placed, it is known that the entire order will arrive on a truck in 6 days.
Currently, the company is ordering 500 units each time an order is placed. What is the total
holding cost for the year using this policy?
A)$4,000
B)$8,000
C)$2,000
D)$400
6)Rolf Steps is the production manager for a local manufacturing firm. This company produces
staplers and other items. The holding cost is $2 per unit per year. The cost of setting up the
production line for this is $25. There are 200 working days per year. The production rate for this
product is 80 per day. If the production order quantity is 200 units, what was the daily demand
(rounded to the nearest whole unit)?
A)6 units
B)9 units
C)8 units
D)7 units
7)Mark Achin sells 3,600 electric motors each year. The cost of these is $200 each, and demand is
constant throughout the year. The cost of placing an order is $40, while the holding cost is $20 per
unit per year. There are 360 working days per year and the lead-time is 5 days. If Mark orders 200
units each time he places an order, what would his average inventory be (in units)?
A)100
B)120
C)200
D)60
8)Judith Thompson, the manager of the student center cafeteria, has added pizza to the menu. The
pizza is ordered frozen from a local pizza establishment and baked at the cafeteria. Judith
anticipates a weekly demand of 10 pizzas. The cafeteria is open 45 weeks a year, 5 days a week.
The ordering cost if $15 and the holding cost is $0.40 per pizza per year. The pizza vendor has a
4-day lead-time and Judith wants to maintain 1 pizza for safety stock. What is the optimal reorder
point?
A)9
B)10
C)4
D)8
TRUE/FALSE. Write 'T' if the statement is true and 'F' if the statement is false.
9)We can usually determine an appropriate safety stock even if we are unable to accurately assess the
actual cost of a stockout.
10)Economic order quantity (EOQ) analysis has recently become practical as a consequence of
high-speed computers.
11) Consider the following linear programming problem:
Maximize 5X + 6Y
Subject to: 4X + 2Y 420
1X + 2Y 120
all variables 0
Which of the following points (X,Y) is in the feasible region?
A) (105,5)
B) (100,10)
C) (30,60)
D) (0,210)
E) none of the above
12) The condition when there is no solution that satisfies all the constraints is called
A) dependency.
B) redundancy.
C) boundedness.
D) optimality.
13) If the addition of a constraint to a linear programming problem does not change the solution, the
constraint is said to be
A) unbounded.
B) bounded.
C) redundant.
D) non-negative.
E) infeasible.
14) Consider the following linear programming problem:
Maximize 10X + 30Y
Subject to X + 2Y 80
8X + 16Y 640
4X + 2Y 100
X, Y 0
This is a special case of a linear programming problem in which
A) there is a redundant constraint.
B) there are multiple optimal solutions.
C) there is no feasible solution.
D) this cannot be solved graphically.
15) Which of the following is not acceptable as a constraint in a linear programming problem
(maximization)?
Constraint 1 X + XY + Y 12
Constraint 2 X - 2Y 20
Constraint 3 X + 3Y = 48
Constraint 4 X + Y + Z 150
A) Constraint 1
B) Constraint 2
C) Constraint 3
D) Constraint 4
16) Consider the following linear programming problem:
Maximize 12X + 10Y
Subject to: 2X + 3Y 480
4X + 3Y 360
The maximum possible value for the objective function is
A) 1560.
B) 360.
C) 480.
D) 1520.
17) Sensitivity analyses are used to examine the effects of changes in
A) technological coefficients.
B) contribution rates for each variable.
C) available resources.
D) all of the above
18) Infeasibility in a linear programming problem occurs when
A) there is an infinite solution.
B) more than one solution is optimal.
C) the feasible region is unbounded.
D) a constraint is redundant.
E) there is no solution that satisfies all the constraints given.
19) Which of the following is not acceptable as a constraint in a linear programming problem
(minimization)?
Constraint 1 X + Y 12
Constraint 5 2X - 3Y + Z > 75
E) Constraint 5
20) When appropriate, the optimal solution to a maximization linear programming problem can be
found by graphing the feasible region and
A) moving the isoprofit lines towards the origin in a parallel fashion until the last point in the
feasible region is encountered.
B) locating the point that is highest on the graph.
C) finding the profit at every corner point of the feasible region to see which one gives the
highest value.
D) none of the above
E) all of the above
21) Which of the following is not one of the steps in formulating a linear program?
A) Graph the constraints to determine the feasible region.
B) Use the decision variables to write mathematical expressions for the objective function and
the constraints.
C) Define the decision variables.
D) Identify the objective and the constraints.
E) Completely understand the managerial problem being faced.
22) Which of the following functions is not linear?
A) 2X - 5Y + 2Z
B) 2X + 5YZ
C) 3X + 4Y + Z - 3
D) Z
E) 5X + 3Z
23) Two models of a product - Regular (X) and Deluxe (Y) - are produced by a company. A linear
programming model is used to determine the production schedule. The formulation is as follows:
Maximize profit = 50X + 60Y
Subject to: 8X + 10Y 800 (labor hours)
X + Y 120 (total units demanded)
4X +10Y 500 (raw materials)
The optimal solution is X=100, Y=0.
Which of these constraints is redundant?
A) the second constraint
B) the first constraint
C) the third constraint
24) Typical resources of an organization include ________.
A) warehouse space utilization
B) labor volume
C) machinery usage
D) raw material usage
25) In a minimization problem, when one or more of the solution variables and the cost can be made
infinitely large without violating any constraints, then the linear program has
A) alternate optimal solutions.
B) an infeasible solution.
C) a redundant constraint.
D) an unbounded solution.
26) The addition of a redundant constraint lowers the isoprofit line.
27) Resource restrictions are called constraints.
28) Resource mix problems use LP to decide how much of each product to make, given a series of
resource restrictions.
29) Management resources that need control include machinery usage, labor volume, money spent,
time used, warehouse space used, and material usage.
30) When two or more constraints conflict with one another, we have a condition called
unboundedness.
Hi,Correct option is DRegards
Oh, there are 30 questions in total. I think only first of them got posted when requested me.
I apologize. I had to go in and edit my questions. There are 30 questions in total.
Ok, no problem. I'll review the questions and let you know.
And could you please attach the original document for the questions? Inequality signs are missing from all constraint problems.
It will not let me attach.
For 11 it has
5x +6y
4x + 2y (< over -) 420
1x + 2y (< over -)120
all variables (> over -)
For 14 it has
10x + 30y
x +2y (< over -) 80
8x + 16y (< over -) 640
4x + 2y (> over -) 100
x, y (> over -) 0
For 15
Constraint 1: x+xy + y (> over -) 12
Constraint 2: x-2y )> over -) 20
Constraint 3: x+3y =48
Constraint 4: x+y+z (< over -) 150
for 16
maximize subject to:
12x+10y
2x +3y (< over -) 480
4x +3y (< over -) 360
all variables (> over -) 0
for 19
constraint:1 x+y (> over -) 12
constraint 2: x-2y (> over -)20
constraint 3: x+3y=48
constraint 4: x+y+z (< over -) 150
constraint 5: 2x-3y +z > 75
for 23
maximize profit = 50x+60y
subject to: 8x+10y (< over -) 800 (labor hours)
x+y (< over -) 120 (total units demanded)
4x + 10y (< over -) 500 (raw materials)
x, y (> over -)0
the optimal solution is x=100, y=0
Could you please mention the deadline for this question?
Midnight Wed, Dec 7.
Ok.
Could you please tell me what your current status is with these questions?
I can help with most of the questions, but these are quite many given most of them require mathematical calculations. At your current offer I can answer 6-7 questions at a time. That would be 4-5 sets for total of 30 questions. Please let me know if it's acceptable to you as multiple sets.Regards
I am not satisfied with that. I have seen your work and you have answered more then 20 for the same amount of money. I would be satisfied with the first 20 questions from this list.
I'm not sure. I might have done it some time before, or because I'd have worked with him on many questions before. Anyways, I'd opt out and open this to other experts who might be willing to help with these all questions at your current offer.Regards
If this was the case you should have told me earlier on. My DEADLINE is tonight.
Not only that but a good tip would have been included for your efforts.
Ok. Could you specify the amount you're willing to add as bonus before I start working on it?
I was planning on doing a $10.00 tip. That is over 20%
Alright, I hope you'd be able to afford more. What time are the answers due? And as I said before, I'm not sure about a few. I hope that's ok with you.
The ones you can't answer please leave blank so I know which ones thy are. They are due by midnight.
Ok
THIS ANSWER IS LOCKED!You need to spend $3 to view this post. Add Funds to your account and buy credits.
Experience: B.Tech
I will check them out as soon as I get home from work. Thank you very much and I will definatly aend you a bonus :)
Ok, I'll look forward to it, as it was quite a time consuming task.