How JustAnswer Works:
  • Ask an Expert
    Experts are full of valuable knowledge and are ready to help with any question. Credentials confirmed by a Fortune 500 verification firm.
  • Get a Professional Answer
    Via email, text message, or notification as you wait on our site.
    Ask follow up questions if you need to.
  • 100% Satisfaction Guarantee
    Rate the answer you receive.
Ask Law Educator, Esq. Your Own Question
Law Educator, Esq.
Law Educator, Esq., Lawyer
Category: Consumer Protection Law
Satisfied Customers: 115464
Experience:  Attorney experienced in commercial litigation.
10285032
Type Your Consumer Protection Law Question Here...
Law Educator, Esq. is online now
A new question is answered every 9 seconds

A construction lien was placed on our property in Utah. No

Customer Question

A construction lien was placed on our property in Utah. No order of commencement was made with the state. The company owes me money for over paying them. The shower pan they installed is crocked. What do I need to do?
Submitted: 1 year ago.
Category: Consumer Protection Law
Expert:  Law Educator, Esq. replied 1 year ago.

Thank you for your question. I look forward to working with you to provide you the information you are seeking for educational purposes only.

If they have placed the lien, but they arethe party in breach of the construction contract for their negligent work and owe you money for over payment, then you need to file suit in court for the cost to fix the negligently installed shower,the overpayment and also asking the curt to remove the improperly placed lien. For improperly placing the lien you can also seek attorney's fees as part of your damages, so I would suggest engaging a local construction or consumer protection law attorney to represent you and get this matter resolved and the negligent work corrected as well.