How JustAnswer Works:
  • Ask an Expert
    Experts are full of valuable knowledge and are ready to help with any question. Credentials confirmed by a Fortune 500 verification firm.
  • Get a Professional Answer
    Via email, text message, or notification as you wait on our site.
    Ask follow up questions if you need to.
  • 100% Satisfaction Guarantee
    Rate the answer you receive.
Ask Ulysses101 Your Own Question
Ulysses101, Lawyer
Category: Canada Law
Satisfied Customers: 3285
Experience:  11 years experience in Canada family law, plus criminal, civil, and employment
Type Your Canada Law Question Here...
Ulysses101 is online now
A new question is answered every 9 seconds

In Ontario can a valid construction lien be registered 60

Customer Question

in Ontario can a valid construction lien be registered 60 days from the last day of work!!
Submitted: 1 month ago.
Category: Canada Law
Expert:  Ulysses101 replied 1 month ago.

Hello, thank you for the question.

No, it's 45 days from the last date of work or delivery of goods to the site, I'm afraid.

If one misses that 45 day period, then one either has to try to justify a later "last date", or bring an action under regular civil law rules of 2 years.

Does that answer you?